Pools

Renovation of the "Triton" swimming pool in Evere

Evere / 2013

Renovation of the tanks and a part (solarium side) of the outdoor carpentry of the pool, technical equipment for water treatment.

The work performed was as follows:

  • Construction and repair of concrete,
  • Replacement of beach floor tiles,
  • Laying a coating in the two tanks of the pool,
  • Appropriation of hydraulic water treatment systems of the pool water up to 50 cm outside the tanks,
  • All the accessories and the work of completion peripheral to the basins,
  • Outdoor carpentry work,
  • Replacement of the sliding outer frames of the pool (only the lower part),
  • Replacement of a cafeteria frame and door (solarium side),

Technical equipment for water treatment:

  • Installation of a chloramine reduction system by UV treatment of the large basin,
  • adaptation of exchangers,
  • piping,
  • Circulation pump.

Back