Transformation and renovation of the Hotel de Vill de Braine-Le-Comte

Braine-Le-Comte / 2015

The work in general consisted of:

  • The extension of the secondary staircase towards the 2nd floor,
  • The renewal of current sanitary facilities,
  • The replacement of all the outer frames of the recent wing,
  • The insulation, and the coating on insulation, the treatment of the basement, this for the 3 facades.

Basement:

  • The closure of the porch to install the new high voltage cabin and create a new room,
  • The removal of the current HT cabin and its move to the new HT premises.

Ground floor:

  • The demolition of the current RF partition, the replacement of the office door 0.16 (RF door),
  • The Sanitary transformation,
  • The realization of the bay towards the hall of the wickets.

1st Floor:

  • The realization of the staircase towards the 2nd floor,
  • The Sanitary transformation,
  • The replacement of the 2 office doors 1.09 and 1.10 (RF doors),
  • The wedding hall is equipped to accommodate temporary offices (outside the company).

2nd Floor:

  • The landing slab of the new staircase,
  • The extension of the corridor to access the archives and the new staircase,
  • The partitioning of the archives in relation to the new staircase and corridor,
  • The Sanitary transformation,