Saint-Christophe Church of Fontaine l'Eveque - consolidation work of the Church

Fontaine - L’Evêque / 2005

The work of the first phase consisted of:

  • Repair of all the roofs except the one of the tower,
  • Exterior repairs of the masonry of the transept and choir,
  • Stabilization of the building by injecting a mineral grout (lime-based) to fill the gaps between the walls (26 M3) plus 4 M3 for the crossing of the transepts,
  • Injection of mineral grout in buttresses with pinning or anchoring using 30X30 stainless steel bars 30x30,
  • Reinforcement of the vaults and arches with stainless steel rods diameter 4 through the ceilings and recalled in a lime based screed containing a metal mesh.

All drilling is carried out underwater using horizontal electric drills and vertical oil turbines.

The work of the second phase consisted of:

  • replacement of the roof and structure of the bell tower,
  • The stabilization of the central nave, the lateral nave and the tower,
  • Renovation of exterior masonry.